EV chargers · Installation
Looped supply and the DNO.
Why your charger is on hold.
Your electrician has looked in the meter box and said the install has to wait for the DNO. It is a common moment and it is rarely anyone's fault. Here is what it means and how to check you are getting the full story.
The short answer
A looped supply means you share the cable from the street with a neighbour. Before a charger goes on, the network operator usually gives your home its own cable. Your electrician cannot do that work. They can only ask for it.
Think of it like a shared driveway
Two houses share one driveway to the road. That works fine for a couple of cars a day. Park a lorry on it every night and next door struggles to get out.
A looped supply is that shared driveway for electricity. A kettle or an oven is a car. An EV charger running for six hours is the lorry. The network operator would rather give each home its own driveway first.
Who does what
- The DNO (network operator): owns the street cable, the main fuse and the sealed cut-out in your meter box. Only it can unloop a supply or upgrade the main fuse.
- Your energy supplier: owns the meter and sends the bill. It does not own the cable and cannot unloop it, though it fits the smart meter you need for an EV tariff.
- Your installer: checks the meter box, tells the DNO about the charger and applies for any work needed. Then they wait like you do.
Not sure who your network operator is? The Energy Networks Association lookup tells you from your postcode.
Is my electrician telling the truth?
Almost always, yes. A looped supply is easy to spot and a good installer would rather tell you than fit a charger that breaks the rules. If you want peace of mind, ask for three things:
- 1. A photo of your cut-out, showing the extra cable heading to next door.
- 2. The DNO reference number for the application.
- 3. The date it was submitted.
With the reference you can contact the network operator yourself for an update. A straightforward installer will share all three without fuss.
The details
It depends on the network operator and how complex the work is. Straightforward cases usually take around 3 to 12 weeks. Access, permits or neighbouring properties can stretch it to several months or longer.
In Great Britain standard unlooping is usually free, as the network operator generally covers the cost. Your neighbour does not pay either. Additional work may be chargeable, so confirm the position with your local network operator.
Some older homes have a 60 amp main fuse. The operator may upgrade it to 80 or 100 amps at the same time. Many chargers can also manage the load by slowing down when the house is busy.
Usually just let the operator in, if the work is in their meter box. Both homes may have a short planned power cut on the day.
What to do while you wait
- Ask early: if you are still choosing the car, get the meter box checked now. Photos are often enough.
- Sort the smart meter: you need one for most EV tariffs, and it is a separate job with your supplier.
- Bridge the gap: public charging and the occasional 3-pin top-up cover a short wait, but neither is a long-term fix.
The verdict
A looped supply is a pause, not a problem. The work is usually free, the wait is the only real cost and a good installer will keep you in the loop. Ask for the reference number and you will always know where you stand.
Quick answers
It is when your home shares its electricity cable from the street with a neighbour. It was a common way to save cable when houses were built and is still found in many UK homes.
A charger can draw a lot of power for hours at a time. On a shared cable that load is shared with next door, so the network operator usually wants each home on its own supply first.
The Distribution Network Operator owns the cables, substations and the main fuse that bring power to your street and your meter. It is not your energy supplier and you do not pay it directly.
In Great Britain standard unlooping is usually free, as the network operator generally covers the cost. Additional work may be chargeable, so confirm the position with your local network operator.
Straightforward cases usually take around 3 to 12 weeks. Access, permits or neighbouring properties can stretch it to several months or longer.
Ask for a photo of your meter cut-out and the DNO reference number for the application. You can then contact the network operator yourself and ask for an update on that reference.